Edit Resource: DurationOverrideEfficiency

Description

The DurationOverrideEfficiency attribute under EditResource defines the efficiency factor of the override for the resources with DurationOverrideType = EfficiencyFactor.

Parameters

ParameterDescription
DurationOverrideEfficiencyThe efficiency factor as a decimal.

Examples

The resource will override a task's duration based on an efficiency factor of 1.3. If a task with a 60s duration uses OpsTeam, the task duration will now be 46s.

PATCH api/resource/OpsTeam

Body:

{

"DurationOverrideEfficiency" : "1.3"

}